US data centres ‘are short six NYCs of electricity’

With great power comes great implausibility
00:00

{"text":[[{"start":6.16,"text":"Not everything that Elon Musk says is stupid. Sometimes it’s just obvious. Here he is, speaking about AI data centres at the G20 Innovation Ministerial Summit in North Carolina a couple of weeks ago:"}],[{"start":20.701,"text":"There’s quite a crisis of power. [ . . . ] The consensus at this point is that there will be a significant power shortfall next year. So, not like distant future. I believe the consensus estimate among analysts who follow the AI space very closely is that there will be at least a 15-gigawatt shortfall of power in 2027 for AI chips. The rate at which AI chips [are] being produced has been rising incredibly rapidly. They’re rising on the order of 40 to 50 per cent a year. But power available outside of China has been rising at 10 per cent to 20 per cent a year. Obviously, the faster-rising thing will eventually overwhelm the slower-rising thing."}],[{"start":62.64,"text":"Unusually for Musk, he makes a reasonable point but has lowballed the numbers."}],[{"start":66.75,"text":"Morgan Stanley analysts today revised their model for how much power would be needed to switch on the chips it projects will be sold. They now estimate, based on a total data-centre power requirement of 257 GW by 2028, a gap of between 30 and 40 per cent between US capacity and sales projections. Or to put it in layperson’s terms:"}],[{"start":91.68,"text":"New York City demands 5.5-6 GW of baseload power: we are short power by six New York Cities."}],[{"start":95.411,"text":"And that’s using their mid-estimate for innovative “time-to-power” solutions. Absent such mitigation measures, the estimate rises to 10 NYCs:"}],[{"start":null,"text":"

"}],[{"start":104.4,"text":"The MS team led by Stephen Byrd had previously estimated a US power supply shortfall of 38GW through 2028. Its new figures factor in a heavier draw from more complex servers built around Nvidia’s Vera Rubin and Rubin Ultra architectures, which threaten to increase the IT power demand by fivefold from 2025 to 2028:"}],[{"start":null,"text":"
"}],[{"start":126.283,"text":"Maybe this seems counterintuitive. Nvidia has said its Vera Rubin systems can deliver 30 times higher throughput per MW for agentic workloads than its predecessor."}],[{"start":134.64,"text":"Unfortunately for grid operators, the improved chip efficiency means data centre operators will improve margins by packing more processing power into the same footprint, Morgan Stanley assumes. System designers “use [GPU] efficiency gains to deploy more computing capacity rather than reduce electricity consumption”, it says."}],[{"start":156.645,"text":"Data centres have tended to host servers of eight GPUs each. The next generation of integrated hardware comes in similar-sized boxes, but will draw more juice per installation and run a lot hotter. Nvidia’s Vera Rubin NVL72 server rack bundles together 72 GPUs with CPUs, network switches and hardware for power management and cooling in one miniaturised package. According to CoreWeave, a typical server rack “produces as much heat as 10-25 ovens running simultaneously”."}],[{"start":189.245,"text":"The unit economics of replacing legacy cards make sense. Switching from Nvidia’s Hopper family (released Q3 2022) to Rubin Ultra (due H2 2027) could lower the all-in cost of a processor operation by 94 per cent, the team estimates. Per-chip token yields improve by approximately 15 times, so in spite of the higher operating costs there’s still a sixfold improvement in tokens per watt."}],[{"start":215.92,"text":"But from 2027, denser racks require “a step change in power demand”, Morgan Stanley says. It’s a textbook example of Jevons paradox, the phenomenon whereby improved efficiency makes a resource cheaper to use, which increases consumption and undoes the savings from individual efficiency."}],[{"start":238.57,"text":"Fenyman, Nvidia’s next next chip architecture, is scheduled for launch in the second half of 2028. It’ll be another step change, Morgan Stanley says: the same dynamics will increase US power demand year-on-year by a further 40 per cent in 2029, Byrd and team estimate. They’re then looking at a cumulative power shortfall of 107GW (or approximately 18 NYCs)."}],[{"start":259.28,"text":"Per the first graph, “time to power” solutions could close the deficit. Bloom Energy’s fuel cells have the potential to add 5GW to supply by 2028, with a further 2GW coming via data centres being placed behind-the-meter in nuclear plants."}],[{"start":275.6,"text":"That still leaves a cumulative 17GW shortfall in Morgan Stanley’s mid-case innovative portfolio for 2028. It needs to be filled by a raft of so-far-unannounced programmes to deliver gas turbines and off-grid generators that don’t yet exist in commercial forms. Spin the estimates forward a year, and the vapourware in the numbers increases to a cumulative 24GW:"}],[{"start":null,"text":"
"}],[{"start":299.47,"text":"The way to play the theme is to invest in nearly any company that has a viable plan to make or sell energy, the bank says. These include “powered shell providers” (which we used to call bitcoin miners), novel generation companies and equipment suppliers."}],[{"start":315.83,"text":"This being a Morgan Stanley note, it also recommends a hit-and-hope buy of SpaceX. The telecoms company recently broke ground on a foundry in Texas to make its own gas turbine blades and vanes, and Musk spent an estimated $1bn of his own money in July to buy off-grid gas and diesel generator supplier APR Energy, it highlights, while cautioning that these are multiyear projects."}],[{"start":339.12,"text":"The argument presented is that AI is a virtuous circle. Each new generation of hardware will improve the unit economics of milling tokens, increasing margins for data centre operators and improving AI adoption rates. Improved adoption means more complicated workloads, which adds to infrastructure demands."}],[{"start":359.156,"text":"“However,” the team add in bold, “all of these advancements converge on one central issue: if we cannot close the power shortfall, the expected pace of improvement and adoption may not fully materialise in line with market expectations.”"}],[{"start":372.96,"text":"They probably don’t need to spell out what happens to all those big tech off-balance-sheet guarantees in that scenario. Obviously, the faster-rising thing will eventually overwhelm the slower-rising thing."}],[{"start":389.04,"text":""}]],"url":"https://audio.ftcn.net.cn/album/a_1790048457_3357.mp3"}

版权声明:本文版权归FT中文网所有,未经允许任何单位或个人不得转载,复制或以任何其他方式使用本文全部或部分,侵权必究。

国际足联与Netflix:体育界的下一对强强搭档?

另请阅读今日新闻通讯:西班牙足球的房地产布局。

本周图表:法国政府债券与企业债券收益率趋于一致

一些公司的债券收益率如今低于政府债券。

为什么17并非产业政策的神奇数字

缺乏重点恐将拖累日本首相高市早苗的增长战略。

亿万富豪慈善热潮兴起,但附带条件

营造公众善意有助于建设数据中心、开发AI聊天机器人,并尽量减少政府干预。

澳大利亚财长:中等强国应加强合作,避免受制于地缘政治

吉姆•查默斯认为,保障经济安全、强化供应链将使消费者受益。

极飞科技希望每位农民“都拥有自己的机器人”

中国初创企业极飞科技认为,无人驾驶植保无人机有望应对劳动力日益短缺和气温不断上升的问题。
设置字号×
最小
较小
默认
较大
最大
分享×